Framatome has obtained a decision from the French Nuclear Safety Authority (ASN) to lift the suspension of the test certificate for the secondary part of one of the steam generators on reactor No. 2 at the Fessenheim NPP.

In July 2016, the ASN took the decision to suspend the test certificate for this component as a precautionary measure subsequent to a deviation found in the internal manufacturing records for one of the parts used in the assembly of this component. This deviation was identified by Framatome as part of the review of the manufacturing records at the Le Creusot site. This deviation concerned the cropping rate of the steel ingot used to manufacture the part, known as a shell.

A program mobilizing Framatome's testing and production capacities and expertise

Technical analyses conducted by experts from Framatome since 2016 have concluded that the deviation detected did not compromise the integrity of the component in operation. However, in order to substantiate matters, two shells with identical characteristics (steel grade, ingot weight, dimensions of the part) were cast and forged at Le Creusot site. Chemical analyses and mechanical tests (tensile and impact-strength tests) were carried out on these parts.

The complete proposed test program to substantiate the serviceability of this part was the subject of discussions with the ASN on an ongoing basis in order to obtain agreement from the authority on the methodology used. The ASN was kept informed by Framatome of the actions taken and the results of the analyses carried out.

On the basis of its analyses, and in coordination with EDF, Framatome put together a file enabling the suspension of the test certificate to be lifted by the ASN. This file was analyzed by a cross-disciplinary standing group of experts on February 27, 2018. On March 9, 2018, the ASN published its decision confirming the lifting of the suspension of the certificate for the steam generator.

 

About Framatome

Framatome is an international leader in nuclear energy recognized for its innovative, digital and value added solutions for the global nuclear fleet. With worldwide expertise and a proven track record for reliability and performance, the company designs, services and installs components, fuel, and instrumentation and control systems for nuclear power plants. Its more than 16,000 employees work every day to help Framatome’s customers supply ever cleaner, safer and more economical low-carbon energy.