Flamanville 3 is France’s first generation III+ EPR

View of Flamanville 3, 2 and 1

View of Flamanville 3, 2 and 1 - © EDF

The Flamanville 3 (FA3) project is part of the French nuclear fleet renewal programme. Located in the Cotentin Peninsula, it is one of the major industrial achievements associated with EPR technology in Europe.

Framatome has supported EDF in the design, construction, and commissioning of the reactor by supplying the Nuclear Steam Supply System (NSSS) and the nuclear fuel. The project has mobilised the full range of the Group’s expertise, including design and safety engineering, manufacturing of major components, supply chain management, on-site construction activities, physical and startup testing, as well as the deployment of operational and safety Instrumentation & Control (I&C) systems.

This commitment continues beyond the start of operation. Installed Base teams provide technical support, operational engineering, maintenance, modifications, and experience feedback management. This continuity demonstrates Framatome’s ability to support its customers throughout the entire reactor lifecycle, from design and construction to operation.

Today, the EPR reactor stands as a benchmark for safety, operational performance, and industrial excellence. It represents the most advanced standard of pressurised water reactor technology currently in operation.

Key Milestones

  • 2005: Signature of the Nuclear Steam Supply System (NSSS) contract
  • December 2007: First concrete pour
  • July 2013: Reactor building dome installation
  • May 2014: First control room commissioning tests
  • September 2014: Installation of the first steam generator
  • November 2014: Pressurizer installation in the reactor building
  • April 2015: Installation of the three steam generators
  • Summer 2015: Completion of primary circuit mechanical erection
  • February 2016: Delivery of the reactor vessel head to site
  • April 2016: Delivery of the control rod drive mechanisms
  • March 2017: Start of integrated testing with reactor vessel flushing operations
  • October 2017: Start of open-vessel functional testing
  • December 2017: Start of hot functional testing
  • August 2020: Start of repairs and upgrading of the Main Secondary System welds
  • June 2021: Delivery of the full fuel load
  • May 2023: Completion of repairs and upgrading of the Main Secondary System welds
  • October 2023: Start of overall requalification testing
  • May 2024: Issuance of the Nuclear Steam Supply System (NSSS) Certificate of Conformity
  • May 2024: Fuel loading authorization granted by the French Nuclear Safety Authority (ASN)
  • September 2024: First criticality of Flamanville 3
  • December 2024: First connection to the electrical grid
  • May 2025: Grid stability loss test (BAS108)
  • July 2025: Achievement of the 60% Nominal Power milestone
  • 14 December 2025: Achievement of 100% Nominal Power
  • 26 April 2026: Completion of the Startup Test Program